This page contains documents which are currently available for public review and comment. These documents will be in Adobe PDF format. Click here to download Acrobat Reader.
REVISED RECOMMENDED INTERCHANGE DESIGN (Jan 2011)
download Revised Recommended Interchange Design

RECOMMENDED INTERCHANGE DESIGN (Oct 2009)
download Recommended Interchange Design

ALTERNATIVES
During the development of the functional design study four alternatives have been proposed for detailed evaluation, these include shifting PTH 1 north, PTH 1 on the same alignment, shifting PTH 1 south, and separate interchanges for PTH 16 & PR 305.
Alternative A: PTH 1 Shift North
download Alternative A

Pros
- No intersections on PTH 1 or PTH 16
- CN Railway and PTH 1 overpasses closer together, requiring less fill on PTH 16
- Minimizes disturbance to wildlife habitat
Cons
- Major property impacts including removal of one residential farmyard
- Potential stream channel re-alignment (PTH 1)
- Potentially disruptive to know sensitive habitat
Alternative B: PTH 1 on Existing Alignment
download Alternative B

Pros
- No intersections on PTH 1 or PTH 16
- Utilize existing PTH 1 Eastbound lanes and Rat Creek crossing for Service Road
- Property impacts minimized
- Minimizes disturbance to wildlife habitat
Cons
- Potential stream channel re-alignment (PTH 1)
Alternative C: PTH 1 Shift South
download Alternative C

Pros
- No intersections on PTH 1 or PTH 16
- Utilize existing PTH 1 Eastbound lanes and Rat Creek crossing for Service Road
- Configuration of Westbound to Northbound Ramp and Southbound to Westbound Ramp minimizes width for CN Railway overpass structures
- Minimizes disturbance on Rat Creek
- Eliminates direct access to PR 305
Cons
- Close to suspected environmentally sensitive habitat
- Potential impact to one residential farm yard
Alternative D: Separate Interchanges for Highways 16 & 305
download Alternative D

Pros
- Simplifies traffic operations at PTH 16
- Potential benefit for access to industrial park
- No intersections on PTH 1 or PTH 16
- Re-uses existing PTH 1 Eastbound lanes and maximizes re-use of PTH 1 Rat Creek crossing for Service Road
- Property impacts minimized at PTH 16
- Minimizes impact on wildlife habitat
Cons
- PR 305 realigned
- Requires steam channel re-alignment (PTH 1)
- Potential impacts to three residential farmyards
Evaluation of Alternatives Matrix
download Evaluation of Alternatives Maxtrix

Identified Constraints Map
download Identified Contraints Maps

Estimated Traffic Volumes
download Estimated Traffic Volumes